Laserfiche WebLink
• <br /> s ' <br /> Schedule to Completion: <br /> Aug 5 Begin tower base and anchor forming and. <br /> pouring <br /> Aug 5 Begin assembly of tower steel <br /> Aug 23 Stand up first 120 ' of tower <br /> Sept 15 Finish tower erection to 1000 ' level <br /> Nov 8 Antenna arrives <br /> Nov 22 Antenna installed atop tower <br /> At this moment 7 of the total of 8 truckloads of tower <br /> steel have arrived and have been offloaded at the site, and <br /> substantially more than $100 , 000 in payments have been made <br /> by Channel 47 Television, Inc. for items directly relating <br /> to the tower and its installation. <br /> If I may be of further aid please give me a call . <br /> Regards, <br /> a-36r" <br /> Robert L. Zuelsdorf, P.E. <br /> cc: Bill Schereck <br /> Fred Mohs <br /> AM0802 <br />